The report you requested was not found, or there is more than one product with this report number. Please select from this list of similar report numbers.


[Protest of Any Contract Award Under Army RFP]

B-208418.2,B-213046.2: Apr 23, 1984

A firm protested any award of a contract under a request for proposals (RFP) issued by the Army for aerial targets. The firm also requested reconsideration of a prior decision by GAO which denied its earlier protest regarding the same procurement. The protester contended that: (1) the Army violated Defense Acquisition Regulations by sending an amendment to the RFP to all firms originally solicited...

  • pdf icon View Decision (PDF, 4 pages)
B-208418.2, B-213046.2, APR 23, 1984

B-208418.2,B-213046.2: Apr 23, 1984

IS A MERE PROCEDURAL VIOLATION THAT DOES NOT PREJUDICE ANY OFFERORS. PROTEST ALLEGATION THAT THE SOLICITATION SPECIFICATIONS FAVOR TWO PARTICULAR OFFERORS IS UNTIMELY WHERE THE ALLEGATION IS FILED WITH GAO AFTER THE DUE DATE FOR SUBMISSION OF INITIAL PROPOSALS. REQUEST FOR RECONSIDERATION IS UNTIMELY WHERE IT IS NOT FILED WITHIN 10 WORKING DAYS AFTER THE PROTESTER KNEW OR SHOULD HAVE KNOWN THE BAS...

  • html report icon View Decision (HTML)
U.S. Government Accountability Office (GAO)
  • Press Center
  • Copyright & Terms of Use
  • FOIA Requests
  • Contact Us
  • Privacy Policy
  • Scam Alerts
  • Inspector General
  • Accessibility
  • No FEAR Act Data
  • Restricted Reports
  • Sitemap