B-207353.2:
Sep 8, 1982
A firm requested reconsideration of a decision which dismissed as untimely its protest against the award of a contract. The protester contended that its protest had raised issues significant to procurement practices which should be considered on their merits and that the protest was untimely by only 1 or 2 days. Bid protest procedures require that, when a protest is initially filed with a contract...