B-206243:
Feb 18, 1982
A firm protested the apparent award of a contract for facility construction under an invitation for bids issued by the Air Force. The protester complained that its bid was improperly rejected as nonresponsive for failing to bid on all five items. It argued that a fifth item did not require a bid and that under the circumstances it should have been allowed to modify its bid after the opening date t...