[Protest Alleging Deficiencies in Solicitation]

B-205991: Jun 11, 1982

An individual protested the award of contracts under a request for proposals (RFP) issued by the Army for teaching classes in English as a second language. The protester alleged that there were deficiencies in the solicitation concerned with the contractor's qualifications, performance,and certification requirements. Additionally, the protester alleged that a former employee of the Army should be...

  • pdf icon View Decision (PDF, 3 pages)
B-205991, JUN 11, 1982

B-205991: Jun 11, 1982

FILED AFTER THE CLOSING DATE FOR RECEIPT OF INITIAL PROPOSALS AND MORE THAN 10 DAYS AFTER THE INITIAL ADVERSE AGENCY ACTION IS UNTIMELY UNDER OUR BID PROTEST PROCEDURES. DAKF49-82-R-0010 WAS ISSUED ON NOVEMBER 20. THE CLOSING DATE FOR RECEIPT OF INITIAL PROPOSALS WAS AT 4 P.M. THE PROTEST IS AGAINST ALLEGED DEFICIENCIES IN THE SOLICITATION SUCH AS THE REDUCTION IN CONTRACTOR'S QUALIFICATIONS AND E...

  • html report icon View Decision (HTML)
U.S. Government Accountability Office (GAO)
  • Press Center
  • Copyright & Terms of Use
  • FOIA Requests
  • Contact Us
  • Privacy Policy
  • Scam Alerts
  • Inspector General
  • Accessibility
  • No FEAR Act Data
  • Restricted Reports
  • Sitemap