B-205943:
Jan 12, 1982
A firm protested the rejection of its bid by the Air Force on grounds that delivery after bid opening was due to negligence of a commercial carrier. GAO has held that a bid sent by commercial carrier is considered to be hand-carried and the bidder assumes the risk of late delivery. When late, the bid can only be considered if the late receipt is due to improper Government handling. Therefore, the...