Protest Alleging Apparent Low Bid Is Materially Unbalanced

B-205594.2: Jun 29, 1982

A firm protested the Army's proposed award of a contract for the operation of a transportation motor pool. The protester contended that the proposed awardee's bid should have been rejected as nonresponsive because it was materially unbalanced. The solicitation provided for a base period of 6 months and three option periods. The solicitation further provided for the evaluation of price using the ba...

  • pdf icon View Decision (PDF, 7 pages)
B-205594.2, JUN 29, 1982

B-205594.2: Jun 29, 1982

APPARENT LOW BID ON CONTRACT FOR 6-MONTH BASE PERIOD AND 3 OPTION YEARS IS MATERIALLY UNBALANCED SINCE THERE IS REASONABLE DOUBT THAT ACCEPTANCE OF THIS BID - WHICH HAS SUBSTANTIALLY FRONT-LOADED BASE PERIOD PRICE AND DOES NOT BECOME LOW UNTIL AFTER ALL OPTIONS HAVE BEEN EXERCISED - WILL RESULT IN THE LOWEST ULTIMATE COST TO THE GOVERNMENT. 2. THE SOLICITATION IS MATERIALLY DEFECTIVE AND SHOULD BE...

  • html report icon View Decision (HTML)
U.S. Government Accountability Office (GAO)
  • Press Center
  • Copyright & Terms of Use
  • FOIA Requests
  • Contact Us
  • Privacy Policy
  • Scam Alerts
  • Inspector General
  • Accessibility
  • No FEAR Act Data
  • Restricted Reports
  • Sitemap