Apr 26, 1982
A firm protested the award of a contract under a request for proposals (RFP) issued by the Air Force for pump assemblies. The protester contended that the award was improper, because the RFP limited competition to products manufactured by a previously approved source and because the tests on which the Air Force relied in approving the awardee were inadequate. In addition, the protester contended t...