B-204248:
Aug 12, 1981
A firm protested the adverse agency action of the Department of the Army. The protester did not submit an offer because of some organizational problems. According to the protester, the agency accepted offers without amending or changing the solicitation to correct certain alleged improprieties. A party must be interested under bid protest procedures in order to have its protest considered by GAO....