Request for Reconsideration

B-203523.2: May 10, 1982

A firm requested reconsideration of a prior decision which dismissed its protest as untimely, because it had not been filed within 10 days of the initial adverse agency action. In its request, the protester continued to maintain that timeliness should be determined from the date on which it received a reply to its protest from the General Services Administration. GAO concluded that, since all pros...

  • pdf icon View Decision (PDF, 2 pages)
B-203523.2, MAY 10, 1982

B-203523.2: May 10, 1982

DIGEST: PRIOR DECISION WILL NOT BE RECONSIDERED WHEN THE PROTESTER FACTUAL OR LEGAL GROUNDS WARRANTING ITS MODIFICATION OR REVERSAL. THE PROTESTER WAS "LULLED" INTO BELIEVING THAT ITS REQUEST FOR A DELAY IN THE BID OPENING HAD BEEN GRANTED. BILSOM MAINTAINS THAT IT WAS THEREFORE "UNAWARE THAT ITS REQUESTS HAD AS A PRACTICAL MATTER ALREADY BEEN DENIED IN PART" WHEN IT RECEIVED GSA'S REPLY ON MAY 26...

  • html report icon View Decision (HTML)
U.S. Government Accountability Office (GAO)
  • Press Center
  • Copyright & Terms of Use
  • FOIA Requests
  • Contact Us
  • Privacy Policy
  • Scam Alerts
  • Inspector General
  • Accessibility
  • No FEAR Act Data
  • Restricted Reports
  • Sitemap