B-203399.2:
Jul 1, 1981
A firm requested reconsideration of a GAO decision in which its protest was dismissed as untimely. That protest was directed at the allegedly restrictive nature of the specifications, but was not filed until after the bid opening date, contrary to the requirements of bid protest procedures. The basis for the protester's request for reconsideration was that it had filed a verbal protest prior to bi...