B-203352.2:
Dec 21, 1981
A firm requested reconsideration of a decision which dismissed, as untimely, the firm's protest against a contract award made on a sole-source basis. The firm contended that the protest was not untimely because, even when the protest was filed, it was not in possession of all the information required to form a basis of protest. Alternatively, the firm argued that GAO should consider the merits of...