B-203193:
Jun 3, 1981
A firm protested the award of a contract contending that the agency should have made the award on the basis of the original quotations, that negotiation of the revised requirement without cancellation and solicitation was improper, and that it was inconceivable that the successful bidder would lower its price to reflect the revised work. The procurement was conducted under the small purchase proce...