A firm protested the Army's decision to cancel an invitation for bids. The determination to cancel was based upon a cost comparison analysis from which it was concluded that the work could be performed at a lower cost to the Government through continued use of Government personnel rather than by a contractor. The protester contended that the cost comparison did not comply with applicable Army poli...