B-199600:
Aug 25, 1980
A company protested the award of a contract for hospital sterilizer equipment by the Department of the Army. The initial protest was denied by the Army; and under GAO Bid Protest Procedures, any subsequent protest to GAO must be filed within 10 days of initial adverse agency action. Because the firm did not file a protest within 10 days, the protest was ruled untimely. An untimely protest will be...