Protest against Rejection of Bid Was Untimely

B-192742: Sep 13, 1978

A protester questioned the rejection of its bid as nonresponsive. The protest was not considered because the initial protest to the agency was untimely since it was not filed within 10 days after the basis for protest was apparent...

  • pdf icon View Decision (PDF, 2 pages)
B-192742, SEP 13, 1978

B-192742: Sep 13, 1978

DIGEST: PROTEST IS NOT FOR CONSIDERATION ON MERITS BY GAO WHEN INITIAL PROTEST TO AGENCY IS DETERMINED TO BE UNTIMELY PURSUANT TO 4 C.F.R. SINCE BASIS OF PROTEST WAS KNOWN OR SHOULD HAVE BEEN KNOWN MORE THAN 10 DAYS PRIOR TO FILLING OF INITIAL PROTEST. IT IS FOREST'S CONTENTION THAT IT "MAY AUTHORIZE WHOMEVER (THE FIRM) WISHES TO REPRESENT THE COMPANY.". FOREST WAS INFORMED THAT NO AWARD WOULD BE...

  • html report icon View Decision (HTML)
U.S. Government Accountability Office (GAO)
  • Press Center
  • Copyright & Terms of Use
  • FOIA Requests
  • Contact Us
  • Privacy Policy
  • Scam Alerts
  • Inspector General
  • Accessibility
  • No FEAR Act Data
  • Restricted Reports
  • Sitemap