B-190073:
Nov 23, 1977
DETERMINATION TO CANCEL INVITATION AND TO RESOLICIT REQUIREMENT WAS PROPER WHERE INVITATION CONTAINED CONTRADICTORY (90 AND 120 DAYS) CONTRACT COMPLETION SCHEDULE REQUIREMENTS. LOW BIDDER BID ON THE 120 DAY REQUIREMENT (THE ACTIVITY INTENDED TO REQUIRE 90-DAY COMPLETION) AND OTHER BIDDERS EITHER BID ON 90-DAY REQUIREMENT OR BASIS THEY BID ON IS UNCLEAR. FACT THAT NO BIDDER MADE REQUEST FOR CLARIFI...