B-189581:
Aug 8, 1977
Alleged low bidder objected to the agency's decision not to award them a contract. Since the protest was not filed within 10 working days after the protester was told by the contracting activity that their low bid would not be accepted for award, the protest was untimely and was not considered on its merits...