B-187912:
Aug 17, 1977
The protester complained about the decision to exclude the company from being the supplier of switchgear equipment under a contract award funded in significant part by Federal grant funds. The motivation for the "manufacturer only" requirement for switchgear equipment in this case was prompted by the grantee's stated inability to write an adequate specification. However, it is unfair to prevent co...