B-187573, JANUARY 17, 1977

B-187573: Jan 17, 1977

THEREFORE WHETHER OBJECTIVE EVIDENCE OF COMPLIANCE HAS BEEN PRODUCED IS MATTER COGNIZABLE BY GAO. 2. AFFIRMATIVE DETERMINATION OF RESPONSIBILITY WAS SUPPORTED BY OBJECTIVE EVIDENCE OF COMPLIANCE WITH DEFINITIVE RESPONSIBILITY CRITERION WHERE SUCCESSFUL BIDDER EMPLOYED WELDER HAVING REQUISITE CERTIFICATION. THE IFB WAS FOR THE INSTALLATION OF STEAM LINES AT THE AGRICULTURAL RESEARCH CENTER IN BELTS...

  • html report icon View Decision (HTML)
Protest to Award of Contract to Bidder Claimed to Be Nonresponsible

B-187573: Jan 17, 1977

A company protested the award of a Department of Agriculture contract for installation of steam lines, claiming that the successful bidder did not meet qualifications in the solicitation. The determination of responsibility was found to be reasonable since it was supported by objective evidence...

  • pdf icon View Decision (PDF, 3 pages)
U.S. Government Accountability Office (GAO)
  • Press Center
  • Copyright & Terms of Use
  • FOIA Requests
  • Contact Us
  • Privacy Policy
  • Scam Alerts
  • Inspector General
  • Accessibility
  • No FEAR Act Data
  • Restricted Reports
  • Sitemap