Bidder Will Perform with Own Forces at Least 12 Percent of On-Site Construction Work

B-187407 Mar 03, 1977
Jump To:
Skip to Highlights

Highlights

The award of a GSA contract to a construction firm was protested because of a contention that Weiss failed to prove it will perform the required 12 percent of on-site work. There is no basis to conclude that Weiss is nonresponsive to the 12 percent requirement merely because it has listed subcontractors (other than itself) for all categories of work on the bid form.

Downloads

GAO Contacts

Office of Public Affairs