Hand Delivered Bid Initially Rejected at Bid Opening Was Properly Accepted for Award

B-186941 Mar 04, 1977
Jump To:
Skip to Highlights

Highlights

Award of a construction contract at the Sepulveda, California, Veterans Administration (VA) Hospital was protested on the allegation that the VA improperly accepted the awardee's hand delivered late bid. The lateness was due to improper Government action, and corroborating evidence established that the amount of the bid as submitted at the time of bid opening had not been altered.