B-185952:
Aug 18, 1976
The protester objected to the award of a contract, alleging a conflict of interest on the part of an employee of the low bidder. A conflict of interest was not created by a situation where an engineer whose firm had designed the project specifications was requested by the agency to answer technical questions at a prebid conference and was subsequently hired by the successful bidder as project engi...