Request for Rescission or Reformation of Contract Due to Alleged Bid Errors
B-185796
Jul 06, 1976
Skip to Highlights
Highlights
A company requested reformation or rescission of its contract because of an alleged bid mistake. The request was denied because the contracting officer was not on constructive notice of error; the bids received showed a normal progression from low to high; and the officer was not aware nor should he have been aware that the contractor was not a "stocking or warehousing dealer" and, thus, did not realize certain cost savings.