B-185148, MAR 23, 1976

B-185148: Mar 23, 1976

ASSUMING THAT INITIAL PROTESTS TO PROCURING AGENCY WERE TIMELY FILED UNDER BID PROTEST PROCEDURES. GAO DOES NOT AGREE THAT PROTESTER WAS ENTITLED TO RECEIVE "FULL INFORMATION" RELATING TO FUNDING AVAILABLE FOR AWARD UNDER CANCELLED IFB AND ALL EVENTS SURROUNDING ALLEGED AWARD TO ANOTHER CONCERN UNDER IFB BEFORE FILING PROTEST WITH GAO BECAUSE AGENCY MADE KNOWN ITS FINAL POSITIONS ON PROTESTS TWO W...

  • html report icon View Decision (HTML)
Untimely Protest Regarding Award Under Resolicitation

B-185148: Mar 23, 1976

The protester objected to the award of a contract under a resolicitation, alleging that it should have been awarded the contract under the original solicitation. Assuming that the initial protest filed with the agency was timely, the protester was not entitled to receive full information regarding the award before filing a protest with GAO. The protest was untimely and not for consideration since...

  • pdf icon View Decision (PDF, 4 pages)
U.S. Government Accountability Office (GAO)
  • Press Center
  • Copyright & Terms of Use
  • FOIA Requests
  • Contact Us
  • Privacy Policy
  • Scam Alerts
  • Inspector General
  • Accessibility
  • No FEAR Act Data
  • Restricted Reports
  • Sitemap