B-184739, SEP 24, 1975

B-184739: Sep 24, 1975

PROTEST ALLEGING BIDDER IS NOT RESPONSIBLE DUE TO LACK OF CAPACITY IS NOT FOR CONSIDERATION SINCE GAO HAS DISCONTINUED REVIEW OF BID PROTESTS INVOLVING AFFIRMATIVE RESPONSIBILITY DETERMINATIONS EXCEPT WHERE FRAUD IS ALLEGED. UNLESS FRAUD IS ALLEGED ON THE PART OF THE PROCURING OFFICIALS. THE STANDARDS FOR RESPONSIBLE PROSPECTIVE CONTRACTORS AND THE REQUIREMENTS FOR AFFIRMATIVE RESPONSIBILITY DETER...

  • html report icon View Decision (HTML)
Responsibility of Successful Bidder Questioned

B-184739: Sep 24, 1975

A company objected to the award of a contract, alleging that the successful bidder did not have the capacity necessary to meet the required delivery schedule. The protest was not for consideration since GAO no longer reviews bid protests involving an agency's affirmative determination of responsibility...

  • pdf icon View Decision (PDF, 1 pages)
U.S. Government Accountability Office (GAO)
  • Press Center
  • Copyright & Terms of Use
  • FOIA Requests
  • Contact Us
  • Privacy Policy
  • Scam Alerts
  • Inspector General
  • Accessibility
  • No FEAR Act Data
  • Restricted Reports
  • Sitemap