B-181255:
Jul 17, 1974
A firm protested the award of a contract to the low offeror on the grounds that the procuring agency based its evaluation criteria for terminal value of the awardee's product on market value rather than the Federal supply schedule price. Bid protests must be filed not later than 5 days after the basis for protest is known, or should have been known, whichever is earlier. The basis of the protest w...