B-177858:
Apr 18, 1973
BID AS UNCORRECTED AND CORRECTED WAS STILL LOWEST. KING CO.: REFERENCE IS MADE TO YOUR LETTER OF JANUARY 18. NINE BIDS WERE RECEIVED FOR THIS PROCUREMENT OF THE CONSTRUCTION OF THE MIDWAY-EAGLE LAKE LINE NO. 1.THE AMOUNTS OF THE BIDS WERE AS FOLLOWS: WICO $378. 137 THE GOVERNMENT ESTIMATE FOR THE WORK WAS $432. THE CONTRACTING OFFICER WAS ADVISED BY THE LOW BIDDER THAT A MISTAKE HAD OCCURRED IN TR...