B-159697, SEPTEMBER 6, 1966, 46 COMP. GEN. 194

B-159697: Sep 06, 1966

PROVIDING FOR THE INSTALLATION OF MOVABLE METAL PARTITIONS WITHOUT SPECIFYING THAT THE SUBCONTRACTOR IS REQUIRED TO BE A SPECIALTY SUBCONTRACTOR. IS CONSIDERED AN AMBIGUOUS INVITATION HAVING RESULTED IN ONE BIDDER LISTING A MANUFACTURER'S AGENT AS A SUBCONTRACTOR FOR THE PARTITIONS. 1966: REFERENCE IS MADE TO THE PROTEST OF THE GEORGE HYMAN CONSTRUCTION COMPANY (HYMAN) AGAINST AWARD TO NORAIR ENGI...

  • html report icon View Decision (HTML)
B-159697, AUGUST 22, 1966, 46 COMP. GEN. 156

B-159697: Aug 22, 1966

A PRACTICE THE LISTING OF SUBCONTRACTORS REQUIREMENT WAS AIMED AT. FUTURE INVITATIONS FOR BIDS INVOLVING ARCHITECTURAL CAST STONE OR ANY OTHER MATERIAL THAT IS TO BE FABRICATED AND INSTALLED BY SPECIALTY SUBCONTRACTORS SHOULD REQUIRE BIDDERS TO LIST BOTH THE FABRICATOR AND INSTALLER. 1966: REFERENCE IS MADE TO A LETTER OF JULY 18. BIDS WERE REQUESTED FOR CONSTRUCTION OF AN EXTENSION TO GENERAL OFF...

  • html report icon View Decision (HTML)
U.S. Government Accountability Office (GAO)
  • Press Center
  • Copyright & Terms of Use
  • FOIA Requests
  • Contact Us
  • Privacy Policy
  • Scam Alerts
  • Inspector General
  • Accessibility
  • No FEAR Act Data
  • Restricted Reports
  • Sitemap