B-155343:
Dec 22, 1964
CONTRACTS - DAMAGES - GOVERNMENT LIABILITY - DELAYS THE CLAIM OF A CONTRACTOR FOR THE ADDITIONAL COSTS INCURRED DUE TO THE DELAY BY THE GOVERNMENT IN FURNISHING BORROW MATERIAL UNDER A ROAD CONSTRUCTION CONTRACT IS NOT COMPENSABLE UNDER THE . NOT TO A CLAIM FOR UNLIQUIDATED DAMAGES RESULTING FROM A BREACH OF CONTRACT FOR DELAYS IN PERFORMING UNCHANGED WORK THAT IS ATTRIBUTABLE TO THE GOVERNMENT. W...