B-155343, DEC. 22, 1964, 44 COMP. GEN. 353

B-155343: Dec 22, 1964

CONTRACTS - DAMAGES - GOVERNMENT LIABILITY - DELAYS THE CLAIM OF A CONTRACTOR FOR THE ADDITIONAL COSTS INCURRED DUE TO THE DELAY BY THE GOVERNMENT IN FURNISHING BORROW MATERIAL UNDER A ROAD CONSTRUCTION CONTRACT IS NOT COMPENSABLE UNDER THE . NOT TO A CLAIM FOR UNLIQUIDATED DAMAGES RESULTING FROM A BREACH OF CONTRACT FOR DELAYS IN PERFORMING UNCHANGED WORK THAT IS ATTRIBUTABLE TO THE GOVERNMENT. W...

  • html report icon View Decision (HTML)
B-155343, JUL. 26, 1966

B-155343: Jul 26, 1966

TO THE SECRETARY OF THE INTERIOR: REFERENCE IS MADE TO A LETTER DATED APRIL 20. THE PROPOSED SETTLEMENT WAS ACCEPTABLE TO THE CONTRACTOR. THE MATTER WAS REFERRED HERE PURSUANT TO OUR DECISION TO YOU OF DECEMBER 22. WHILE THE NATIONAL PARK SERVICE OF THE DEPARTMENT OF THE INTERIOR WAS THE CONTRACTING AGENCY. WAS DIRECTLY IN CHARGE OF THE ACTUAL CONSTRUCTION SUPERVISION AND INSPECTION. THE SETTLEMEN...

  • html report icon View Decision (HTML)
U.S. Government Accountability Office (GAO)
  • Press Center
  • Copyright & Terms of Use
  • FOIA Requests
  • Contact Us
  • Privacy Policy
  • Scam Alerts
  • Inspector General
  • Accessibility
  • No FEAR Act Data
  • Restricted Reports
  • Sitemap