B-154837, AUG. 31, 1964

B-154837: Aug 31, 1964

TO THE POSTMASTER GENERAL: REFERENCE IS MADE TO LETTER DATED JULY 29. OR ANY WORK ON HOLIDAYS OR OTHER DAYS WHEN POSTAL INSTALLATIONS ARE CLOSED. * * * THE CONTRACTOR SHALL BE COMPENSATED FOR OVERTIME WORK OF ITS TECHNICAL PERSONNEL ONLY TO THE EXTENT THAT WORK IS ACTUALLY PERFORMED BY ITS EMPLOYEES WITH THE APPROVAL OF THE CONTRACTING OFFICER. AS WELL AS HOURS WORKED ON HOLIDAYS AND OTHER DAYS WH...

  • html report icon View Decision (HTML)
B-154837, JUL. 12, 1965

B-154837: Jul 12, 1965

TO THE POSTMASTER GENERAL: REFERENCE IS MADE TO YOUR LETTER OF MAY 28. AS INDICATED IN YOUR LETTER THE PRESENT CLAIM IS SIMILAR TO THE CLAIM OF ARNOLD H. OR ANY WORK ON HOLIDAYS OR OTHER DAYS WHEN POSTAL INSTALLATIONS ARE CLOSED. THE CONTRACTOR SHALL BE COMPENSATED FOR OVERTIME WORK OF ITS TECHNICAL PERSONNEL ONLY TO THE EXTENT THAT WORK IS ACTUALLY PERFORMED BY ITS EMPLOYEES WITH THE APPROVAL OF...

  • html report icon View Decision (HTML)
U.S. Government Accountability Office (GAO)
  • Press Center
  • Copyright & Terms of Use
  • FOIA Requests
  • Contact Us
  • Privacy Policy
  • Scam Alerts
  • Inspector General
  • Accessibility
  • No FEAR Act Data
  • Restricted Reports
  • Sitemap