B-147297:
Nov 21, 1961
THE CONTRACT WAS ENTERED INTO ON JULY 14. IT WAS SUBSEQUENTLY DETERMINED (ON NOVEMBER 25. THE CONTRACT COMPLETION DATE WAS EXTENDED BY 139 DAYS. IT IS REPORTED THAT THE PARTIAL STOP ORDER AROSE OUT OF A RE-PROGRAMMING OF SPACE IN THE OFFICE BUILDING AND URGENT REQUESTS FROM THE EMBASSY FOR A RECONSIDERATION OF THE FENESTRATION SOLUTION OF THE TWO BUILDINGS. WORK ON THOSE PORTIONS OF THE PROJECT WA...