Navy, Replacement Contract
B-238548: Feb 5, 1991
Additional Materials:
- Full Report:
Contact:
Ralph O. White
(202) 512-8278
WhiteRO@gao.gov
Kenneth E. Patton
(202) 512-8205
PattonK@gao.gov
(202) 512-4800
youngc1@gao.gov
(202) 512-8278
WhiteRO@gao.gov
Kenneth E. Patton
(202) 512-8205
PattonK@gao.gov
Office of Public Affairs
(202) 512-4800
youngc1@gao.gov
The Department of the Navy, Office of General Counsel, asks whether funds originally obligated for a contract in fiscal year 1989 are available for a replacement contract in a subsequent fiscal year where the Navy has determined as a result of a protest that the original contract was awarded improperly and proposes to terminate the original contract for convenience.
We find that the prior year funds may be used accordingly.