Skip to main content

B-215293, JUL 25, 1984, 84-2 CPD 113

B-215293 Jul 25, 1984
Jump To:
Skip to Highlights

Highlights

CONTRACTS - PROTESTS - GENERAL ACCOUNTING OFFICE PROCEDURES - TIMELINESS OF PROTEST - DATE BASIS OF PROTEST MADE KNOWN TO PROTESTER DIGEST: PROTEST FILED ALMOST 1 MONTH AFTER CONTRACTING AGENCY MAILED LETTER CONTAINING BASIS FOR PROTEST IS UNTIMELY UNDER 4 C.F.R. SINCE IT WAS NOT FILED WITHIN 10 WORKING DAYS OF KNOWLEDGE OF BASIS OF PROTEST. REQUIRES PROTESTS TO BE FILED WITHIN 10 WORKING DAYS OF WHEN THE BASIS FOR THE PROTEST IS KNOWN OR SHOULD HAVE BEEN KNOWN. FECHHEIMER'S PROTEST WAS FILED ON MAY 21. IT APPEARS THAT FECHHEIMER'S PROTEST IS UNTIMELY.

View Decision

B-215293, JUL 25, 1984, 84-2 CPD 113

CONTRACTS - PROTESTS - GENERAL ACCOUNTING OFFICE PROCEDURES - TIMELINESS OF PROTEST - DATE BASIS OF PROTEST MADE KNOWN TO PROTESTER DIGEST: PROTEST FILED ALMOST 1 MONTH AFTER CONTRACTING AGENCY MAILED LETTER CONTAINING BASIS FOR PROTEST IS UNTIMELY UNDER 4 C.F.R. SEC. 21.2(B)(2), SINCE IT WAS NOT FILED WITHIN 10 WORKING DAYS OF KNOWLEDGE OF BASIS OF PROTEST.

THE FECHHEIMER BROS. CO.:

THE FECHHEIMER BROS. CO. (FECHHEIMER) PROTESTS THE DECISION BY THE DEPARTMENT OF THE INTERIOR, FISH AND WILDLIFE SERVICE (INTERIOR), TO EXCLUDE ITS PROPOSAL IN RESPONSE TO REQUEST FOR PROPOSALS NO. FWS-9-RF 84- OS-O FROM THE COMPETITIVE RANGE.

WE DISMISS THE PROTEST AS UNTIMELY.

SECTION 21.2(B)(2) OF OUR BID PROTEST PROCEDURES, 4 C.F.R. SEC. 21.2(B)(2) (1984), REQUIRES PROTESTS TO BE FILED WITHIN 10 WORKING DAYS OF WHEN THE BASIS FOR THE PROTEST IS KNOWN OR SHOULD HAVE BEEN KNOWN. INTERIOR MAILED A LETTER ON APRIL 25, 1984, NOTIFYING FECHHEIMER THAT ITS PROPOSAL WOULD NOT BE INCLUDED IN THE COMPETITIVE RANGE. FECHHEIMER'S PROTEST WAS FILED ON MAY 21, 1984-- NEARLY 1 MONTH LATER. ALLOWING A REASONABLE TIME FOR DELIVERY OF INTERIOR'S LETTER, IT APPEARS THAT FECHHEIMER'S PROTEST IS UNTIMELY. HALIFAX ENGINEERING, INC., B-209822, DEC. 15, 1982, 82-2 CPD PARA. 537.

GAO Contacts

Office of Public Affairs