B-205313, NOV 4, 1981

B-205313: Nov 4, 1981

Additional Materials:

Contact:

Ralph O. White
(202) 512-8278
WhiteRO@gao.gov

Kenneth E. Patton
(202) 512-8205
PattonK@gao.gov

 

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

DIGEST: PROTEST NOT FILED WITHIN 10 DAYS AFTER BASIS OF IT IS KNOWN IS UNTIMELY AND WILL NOT BE CONSIDERED. COPYLEASE PROTESTS THE AWARD OF SEVERAL CONTRACTS TO XEROX CORPORATION SHORTLY AFTER THE CBD SYNOPSES WERE PUBLISHED. THIS PROTEST IS UNTIMELY AND WILL NOT BE CONSIDERED. OUR BID PROTEST PROCEDURES REQUIRE THAT A PROTEST BE FILED WITHIN 10 DAYS AFTER THE BASIS OF THE PROTEST IS KNOWN. 4 C.F.R. 21.2(B)(2) (1981). IT IS APPARENT THAT COPYLEASE KNEW OF THE INITIAL CBD SYNOPSIS AND AWARD TO XEROX ON SEPTEMBER 23. COPYLEASE WAS ALSO AWARE OF THE CBD SYNOPSES AND AWARDS FOR THE ADDITIONAL EQUIPMENT. THE PROTEST OVER THE FIRST AWARD SHOULD HAVE BEEN FILED (RECEIVED IN THE GENERAL ACCOUNTING OFFICE) BY OCTOBER 7.

B-205313, NOV 4, 1981

DIGEST: PROTEST NOT FILED WITHIN 10 DAYS AFTER BASIS OF IT IS KNOWN IS UNTIMELY AND WILL NOT BE CONSIDERED.

COPYLEASE CORPORATION OF AMERICA:

COPYLEASE CORPORATION OF AMERICA PROTESTS THE REFUSAL OF CONTRACTING PERSONNEL AT FORT MONMOUTH, NEW JERSEY TO COMPLY WITH THE DEFENSE ACQUISITION REGULATION WHICH IT ASSERTS REQUIRES SOLICITATIONS TO BE SYNOPSIZED IN THE COMMERCE BUSINESS DAILY (CBD) FOR "20 DAYS PRIOR TO AWARD." IN EFFECT, HOWEVER, COPYLEASE PROTESTS THE AWARD OF SEVERAL CONTRACTS TO XEROX CORPORATION SHORTLY AFTER THE CBD SYNOPSES WERE PUBLISHED.

THIS PROTEST IS UNTIMELY AND WILL NOT BE CONSIDERED.

OUR BID PROTEST PROCEDURES REQUIRE THAT A PROTEST BE FILED WITHIN 10 DAYS AFTER THE BASIS OF THE PROTEST IS KNOWN. 4 C.F.R. 21.2(B)(2) (1981). FROM THE INFORMATION SUBMITTED WITH THE PROTEST, IT IS APPARENT THAT COPYLEASE KNEW OF THE INITIAL CBD SYNOPSIS AND AWARD TO XEROX ON SEPTEMBER 23, 1981; THAT BY OCTOBER 5, 1981, COPYLEASE WAS ALSO AWARE OF THE CBD SYNOPSES AND AWARDS FOR THE ADDITIONAL EQUIPMENT. THUS TO BE TIMELY, THE PROTEST OVER THE FIRST AWARD SHOULD HAVE BEEN FILED (RECEIVED IN THE GENERAL ACCOUNTING OFFICE) BY OCTOBER 7, 1981, AND BY OCTOBER 20, 1981, FOR THE SUBSEQUENT AWARD. THE PROTEST WAS DATED OCTOBER 21, 1981, AND IT WAS RECEIVED ON OCTOBER 26.

THE PROTEST IS DISMISSED.