B-244096, May 22, 1991, 91-1 CPD 503

B-244096 May 22, 1991
Jump To:
Skip to Highlights

Highlights

PROCUREMENT - Competitive Negotiation - Offers - Submission time periods - Extension - Propriety DIGEST: Protest of agency's refusal to extend date for receipt of proposals is dismissed where protester did not request a copy of solicitation until 9 days before proposals were due. Even though solicitation was synopsized in the Commerce Business Daily nearly 2 months before. The agency advises us that the RFP was synopsized in the Commerce Business Daily (CBD) on March 22. Was issued on April 16. Proposals were to be submitted by close of business on May 15. When that request was denied. We require a showing that the time allowed was inconsistent with statutory requirements or otherwise unreasonable or insufficient.

View Decision

B-244096, May 22, 1991, 91-1 CPD 503

PROCUREMENT - Competitive Negotiation - Offers - Submission time periods - Extension - Propriety DIGEST: Protest of agency's refusal to extend date for receipt of proposals is dismissed where protester did not request a copy of solicitation until 9 days before proposals were due, even though solicitation was synopsized in the Commerce Business Daily nearly 2 months before, and issued 1 month before, the closing date.

Attorneys

National Medical Staffing, Inc.:

National Medical Staffing, Inc. (NMS) protests the agency's failure to extend the date for receipt of proposals under request for proposals (RFP) No. 246-91-R-0012, issued by the Department of Health and Human Services for dentist services at the Oklahoma City Area Indian Health Service.

We dismiss the protest.

The agency advises us that the RFP was synopsized in the Commerce Business Daily (CBD) on March 22, 1991, and was issued on April 16. Proposals were to be submitted by close of business on May 15. NMS states that it saw the CBD synopsis and requested a copy of the RFP on May 6, and then received the RFP on May 15, the closing date. NMS requested a 30-day extension of the closing date. When that request was denied, NMS filed this protest, alleging that, due to the agency's delay in furnishing the RFP, the closing date should be delayed 30 days.

Where a protester contends that the agency allowed insufficient time for preparation of proposals, we require a showing that the time allowed was inconsistent with statutory requirements or otherwise unreasonable or insufficient, or that it precluded full and open competition. Cajar Defense Support Co., B-240477, Aug. 3, 1990, 90-2 CPD Para. 100.

NMS asserts that the agency's 9-day delay in furnishing the RFP after NMS' request is the reason additional proposal preparation time should be provided. In fact, however, NMS' receipt of the RFP is directly attributable to its failure to request the RFP until more than 6 weeks after it was synopsized in the CBD. In this regard, NMS was on constructive notice of the procurement from the March 22 CBD notice and thus should have been aware of the existence of the RFP at a much earlier date, even before the solicitation was issued on April 16. See U.S. Elevator Corp., B-241772, Mar. 5, 1991, 91-1 CPD Para. 245.

As NMS' inability to prepare a proposal by the closing date thus appears to have been due to its own failure to make reasonable efforts to obtain a copy of the RFP rather than any improper action by the agency, we have no basis to conclude that the agency's refusal to extend the closing date was improper. See Cajar Defense Support Co., B-240477, supra.

The protest is dismissed.