Skip to main content

B-244781, Aug 2, 1991, 91-2 CPD ***

B-244781 Aug 02, 1991
Jump To:
Skip to Highlights

Highlights

A subsequent protest filed with GAO more than 10 days after receipt of letter is untimely. Which provides no specific grounds for the protest and merely promises that details will follow. Asserts that it would have received the contract award had its proposal not been mishandled by the agency. The closing date for receipt of proposals was February 9. When a protest is filed initially with an agency. Jemtec's protest was required to be filed (received) in our Office within 10 days of June 11. Since the protest was not filed at our Office until July 15. It is untimely. Adverse agency action is defined as any action on the part of the contracting agency which is prejudicial to the position taken in a protest filed with the agency.

View Decision

B-244781, Aug 2, 1991, 91-2 CPD ***

PROCUREMENT - Bid Protests - Definition DIGEST: 1. Letter from contracting officer denying agency-level protest constitutes initial adverse agency action, and a subsequent protest filed with GAO more than 10 days after receipt of letter is untimely. PROCUREMENT - Bid Protests - GAO procedures - Protest timeliness - 10-day rule - Adverse agency actions 2. Letter to GAO advising of protester's intention to elevate agency level protest to GAO, which provides no specific grounds for the protest and merely promises that details will follow, does not constitute a protest.

Attorneys

Jemtec Electronics Corp.:

Jemtec Electronics Corp. protests the award of a contract by the Navy to any other bidder under solicitation No. N00104-91-R-M033. Jemtec alleges that the Navy lost the Jemtec proposal, which had been timely delivered to the agency by UPS, and asserts that it would have received the contract award had its proposal not been mishandled by the agency.

We dismiss the protest as untimely.

The closing date for receipt of proposals was February 9, 1991. On March 12, 1991, the protester learned from the Navy that it had awarded the contract to another firm on February 21, 1991, and that Jemtec's offer had not been received by the procuring activity. Jemtec filed a protest with the agency dated March 12. The Navy responded in a letter dated June 4 which denied Jemtec's request that its offer be considered.

When a protest is filed initially with an agency, any subsequent protest to our Office must be filed within 10 days of formal notification of or actual or constructive knowledge of initial adverse agency action. Fed.Reg. 3,759 (1991) (to be codified at 4 C.F.R. Sec. 21.2(a)(3)). For purposes of timeliness, we generally assume delivery of a letter within 1- calendar week of its mailing. See Signal Corp.-- Recon., B-238507.2, Apr. 25, 1990, 90-1 CPD Para. 424. Thus, we presume that Jemtec received the agency's June 4 letter by June 11, and we note that the protester responded to this letter by letter to the agency dated June 20. In order to be timely, Jemtec's protest was required to be filed (received) in our Office within 10 days of June 11. Since the protest was not filed at our Office until July 15, 1991, it is untimely.

While Jemtec claims that the June 4 letter did not constitute a "formal" response to its protest, it clearly qualifies as an adverse agency action within the meaning of our Bid Protest Regulations. Adverse agency action is defined as any action on the part of the contracting agency which is prejudicial to the position taken in a protest filed with the agency. The regulation enumerates specific actions which may constitute adverse agency action, including a decision on the merits of the protest. 56 Fed.Reg. 3,759 supra, (to be codified at 4 C.F.R. Sec. 21.0(f)). The agency's June 4 letter denied Jemtec's March 12 protest, and contrary to the protester's understanding, such a letter was sufficiently "formal" to constitute adverse agency action. See Mackay Communications-Recon., B-238926.2, Apr. 25, 1990, 90-1 CPD Para. 426.

Jemtec also sent a facsimile transmission to our Office, which arrived on June 25, stating that its protest to the Navy was being elevated to our Office for consideration. This transmission provided no grounds of protest, stating merely that: "additional details will follow by fax and/or mail." An announcement of an intention to protest to our Office which does not raise any specific grounds of protest, stating instead that details will follow, cannot be considered a protest, and thus does not toll the 10-day period within which a protest must be filed. See Shankles Eng'g. & Consulting, 68 Comp.Gen. 43 (1988), 88-2 CPD Para. 565; Pacific Fabrications-- Recon., B-224065.2, Sept. 9, 1986, 86-2 CPD Para. 277; Duracell U.S.A., B-225416, Jan. 7, 1987, 87-1 CPD Para. 27.

The protest is dismissed.

GAO Contacts

Office of Public Affairs