Skip to main content

B-247450, Apr 23, 1992

B-247450 Apr 23, 1992
Jump To:
Skip to Highlights

Highlights

Protester thus was not an interested party to protest award to another bidder since it did not question the finding of nonresponsiveness and since at least one other bidder could be awarded the contract if the awardee were found ineligible. We dismiss the protest because the protester is not an interested party. The IFB was issued on August 13. Because it determined that K & M's bid guarantee was unacceptable. Was not an approved surety listed in Department of the Treasury Circular 570. K & M argues that Sellers's bid should have been rejected as nonresponsive because it certified that Sellers was not an emerging small business concern. A bidder is on notice that not all sureties will be considered adequate and it is incumbent upon a bidder to determine which sureties are acceptable to the government.

View Decision

B-247450, Apr 23, 1992

DIGEST: Absence of a protester's corporate surety from Department of the Treasury Circular 570 rendered the bid nonresponsive; protester thus was not an interested party to protest award to another bidder since it did not question the finding of nonresponsiveness and since at least one other bidder could be awarded the contract if the awardee were found ineligible.

Attorneys

K & M Electric Corp.:

K & M Electric Corp. protests the award of a contract to Sellers & Sons under invitation for bids (IFB) No. 678-105-91, issued by the Department of Veterans Affairs (VA) for telephone system site preparation at the VA Medical Center in Tucson, Arizona.

We dismiss the protest because the protester is not an interested party. See 4 C.F.R. Sec. 21.0(a) (1992).

The IFB was issued on August 13, 1991, as a set-aside for emerging small business concerns. /1/ The IFB required bidders to submit a price for a base bid and an alternate bid; the IFB also required the submission of a bid guarantee. Of the six bids VA received by the extended September 20 bid opening date, K & M submitted the apparent low bid. VA rejected the protester's bid as nonresponsive, however, because it determined that K & M's bid guarantee was unacceptable. Specifically, VA found that K & M's corporate surety for its bid guarantee, Pacific International Indemnity Co., Ltd., was not an approved surety listed in Department of the Treasury Circular 570, entitled "Companies Holding Certificates of Authority as Acceptable Sureties on Federal Bonds and as Acceptable Reinsuring Companies." Following the rejection of K & M's bid, VA awarded the contract to Sellers as the next low bidder on January 17, 1992. In its protest, K & M argues that Sellers's bid should have been rejected as nonresponsive because it certified that Sellers was not an emerging small business concern.

Under FAR Sec. 28.202-1(a)(1), all corporate sureties offered for bonds furnished with contracts to be performed in the United States must appear on the list contained in Circular 570. Where, as here, a solicitation provides that failure to provide a bid bond in proper form or amount may be a basis for rejection of a bid, a bidder is on notice that not all sureties will be considered adequate and it is incumbent upon a bidder to determine which sureties are acceptable to the government. American Asbestos Abatement, Inc., B-237613, Nov. 29, 1989, 89-2 CPD Para. 504. a result, the absence of a bidder's corporate surety from Circular 570 renders the bid nonresponsive, notwithstanding the fact that the solicitation does not specifically mention the requirement concerning corporate sureties. Siska Constr. Co., Inc., B-218428, June 11, 1985, 85-1 CPD Para. 669. Here, at the time of bid opening, K & M's corporate surety was not listed in Circular 570. Therefore, K & M's bid was properly rejected as nonresponsive.

K & M argues that the agency acted unfairly because it allowed Sellers to change its size status certification, /2/ which K & M alleges to be a matter of responsiveness, but did not allow K & M to correct the bond defect which made its bid nonresponsive. However, failure to certify size status does not affect a bid's responsiveness because that information is not required to determine whether a bid meets the IFB's material requirements. Insinger Mach. Co., B-234622, Mar. 15, 1989, 89-1 CPD Para. 277. In contrast, as noted above, failure to provide a bond surety listed on Circular 570 is a matter of responsiveness; a nonresponsive bid cannot be made responsive after bid opening. See Lava Tap Cleaning Servs., Inc., B-234728, May 18, 1989, 89-1 CPD Para. 479.

Under the bid protest provisions of the Competition in Contracting Act of 1984, 31 U.S.C. Secs. 3551-3556 (1988), only an "interested party" may protest a federal procurement. That is, a protester must be an actual or prospective supplier whose direct economic interest would be affected by the award of a contract or the failure to award a contract. 4 C.F.R. Sec. 21.0(a). A protester is not an interested party where it would not be in line for contract award were its protest sustained. ECS Composites, Inc., B-235849.2, Jan. 3, 1990, 90-1 CPD Para. 7. Since K & M's bid was nonresponsive, and since the record shows there is at least one other bidder which could be awarded the contract if Sellers were found ineligible for award, K & M lacks the direct economic interest necessary to be an "interested party" eligible to protest the award to Sellers. FeinFocus, USA, Inc., B-245119, Dec. 3, 1991, 91-2 CPD Para. 502; York Int'l Corp., B-235079, Apr. 21, 1989, 89-1 CPD Para. 400. /3/

The protest is dismissed.

/1/ "Emerging small business" means a small business concern whose size is no greater than 50 percent of the normal size standard applicable to the standard industrial classification code assigned to a contracting opportunity. Federal Acquisition Regulation (FAR) Sec. 19.1002.

/2/ Sellers's bid certified it was not an emerging small business] however, it also certified it had gross annual revenues of $2 to 3.5 million and fewer than 100 employees. Since the emerging small business size standard here was gross annual revenues of $8.5 million and fewer than 500 employees, the contracting officer asked Sellers to clarify its certification. Sellers subsequently claimed it had made a clerical error and, based on the information in the bid, the agency found the bid responsive.

/3/ K & M also protests the agency's delay, including two extensions of bid acceptance time, in informing K & M that its bid was nonresponsive. However, this deficiency does not affect the validity of the rejection of the bid. Rodenberg's Floor Coatings, Inc., B-215807, Nov. 23, 1984, 84-2 CPD Para. 548.

GAO Contacts

Office of Public Affairs