Skip to main content

[Protest of Army Corps of Engineers' Decision To Allow Correction of Bid]

B-283857 Published: Jan 18, 2000. Publicly Released: Jan 18, 2000.
Jump To:
Skip to Highlights

Highlights

A firm protested an Army Corps of Engineers' decision to allow the upward correction of a low bid for dining facility construction, contending that the bidder did not submit clear and convincing evidence of the claimed mistake. GAO held that the Corps' decision was reasonable, since the bidder furnished evidence that supported its claim. Accordingly, the protest was denied.

Full Report

Office of Public Affairs