[Protests of EPA Contract Award for Automotive Emissions Testing]

B-274807,B-274807.2: Jan 3, 1997

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

A firm protested the Environmental Protection Agency's (EPA) rejection of its bid and subsequent contract award for automotive emissions testing, contending that EPA unreasonably evaluated the bidders' relative past performance and erroneously eliminated its bid from the competitive range. GAO held that: (1) EPA reasonably evaluated the bidders' past performance; and (2) the protester untimely filed its comments on EPA's report on the supplemental protest more than 5 days after receiving the report. Accordingly, the initial protest was denied and the supplemental protest was dismissed.