[Protest of Navy Contract Award for Bus Stop Shelters]

B-258996: Feb 28, 1995

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

A firm protested a Navy contract award for prefabricated bus stop shelters, contending that the Navy improperly permitted the awardee to correct its bid pricing error. GAO held that the Navy properly permitted the awardee to correct its bid pricing error, since there was clear and convincing evidence of the error and the awardee's intended bid price. Accordingly, the protest was denied.