Skip to main content

[Protest of USDA Rejection of Bid for Emergency Watershed Protection Project]

B-258518 Published: Dec 12, 1994. Publicly Released: Dec 12, 1994.
Jump To:
Skip to Highlights

Highlights

A firm protested the Soil Conservation Service's (SCS) rejection of its bid for performance of an emergency watershed protection project, contending that SCS: (1) should have considered its late bid; and (2) issued a defective solicitation. GAO held that: (1) SCS properly rejected the protester's late bid; and (2) the protester should have clarified the bid opening time prior to bid opening. Accordingly, the protest was denied.

Office of Public Affairs

Topics

Bid rejection protestsDefective solicitationsFederal procurementLate bidsOffer acceptance periodsService contractsSolicitation specificationsSpecifications protestsWater resources conservationWatershed managementBid closing timeSolicitationsBid evaluation protests