[Request for Reconsideration of Dismissed Protest of Air Force Contract Award]

B-256007.2: Jun 28, 1994

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

A firm requested reconsideration of its dismissed protest of an Air Force contract award. GAO had held that the protester untimely filed its comments in response to the Air Force's protest report. In its request for reconsideration, the protester contended that it: (1) received the agency report late; and (2) timely requested an extension to file its comments. GAO held that the protester neither submitted its comments nor requested an extension within 10 working days. Accordingly, the prior decision was affirmed.