A firm claimed reimbursement for its protest costs pursuant to its protest against an Agency for International Development (AID) contract award for facility management. GAO held that the claimant was not entitled to reimbursement of its protest costs, since AID: (1) took corrective action 10 days after the protester filed its protest; and (2) notified the claimant in writing of its action 14 days after the protest filing. Accordingly, the claim was denied.