[Protest of Army Corps of Engineers Rejection of Bid for Housing Improvement]

B-250688: Feb 16, 1993

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

A firm protested the Corps of Engineers' rejection of its bid as materially unbalanced for interior and exterior housing improvement services, contending that the Corps improperly rejected its bid as materially unbalanced, since its bid represented the best value. GAO held that the Corps properly rejected the protester's bid as materially unbalanced, since: (1) acceptance of its bid would result in an advance payment; and (2) it contained significantly below cost line item prices for some required work. Accordingly, the protest was denied.

Sep 16, 2019

Sep 13, 2019

Sep 12, 2019

  • TCG, Inc.
    We dismiss the protest in part and deny the protest in part.