[Protest of VA Rejection of Bid for Medical Center Renovation]

B-250548: Feb 9, 1993

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

A firm protested the Department of Veterans Affairs' (VA) rejection of its bid as nonresponsive for medical center renovation services, contending that VA improperly rejected its bid, since it included an ambiguous bid acceptance period. GAO held that VA properly rejected the protester's bid as nonresponsive, since the protester failed meet the solicitation's bid acceptance period requirement. Accordingly, the protest was denied.