[Request for Reconsideration of Dismissed Protest of BOP Contract Award]

B-250204.2: Dec 22, 1992

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

A firm requested reconsideration of its dismissed protest of a Bureau of Prisons (BOP) contract award for residential community correction services. GAO had held that the protester failed to timely file its protest comments or notify GAO of its continued interest. In its request for reconsideration, the protester contended that GAO improperly dismissed its protest because BOP failed to provide it with a copy of the protest report. GAO held that the protester failed to: (1) show sufficient interest in the protest; and (2) timely act after it did not receive the BOP report. Accordingly, the original decision was affirmed.