[Protest of NAVFAC Selection of A-E Contractor]

B-248973.3: Dec 11, 1992

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

A firm protested the Navy's selection of a firm for negotiation of an architect-engineer contract for design and engineering services, contending that the Navy improperly terminated negotiations with it based on inaccurate prior experience information. GAO held that the Navy's evaluation and decision to terminate negotiations was reasonable. Accordingly, the protest was denied.