[Claim for Protest Costs]

B-247207.2: Oct 23, 1992

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

A firm claimed reimbursement for its protest costs under an Air Force solicitation for a high resolution electron microscope, contending that the Air Force failed to take prompt corrective action pursuant to a sucessful protest. GAO held that the Air Force failed to take prompt corrective action. Accordingly, the claim was allowed.