[Protest of Air Force Two-Step Procurement of GPS Receivers]

B-247913.2: Oct 13, 1992

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

A firm protested an Air Force solicitation for Precise Lightweight Global Positioning System Receivers, contending that the: (1) procurement was improper, because the Air Force erroneously classified the required item as an nondevelopmental item; and (2) Air Force improperly required bid samples. GAO held that the: (1) Air Force reasonably classified the required items; and (2) protester was not sufficiently interested to challenge the bid sample requirement, since it could not provide the required product as a nondevelopmental item. Accordingly, the protest was denied in part and dismissed in part.

Sep 17, 2019

Sep 16, 2019

Sep 13, 2019

Sep 12, 2019

  • TCG, Inc.
    We dismiss the protest in part and deny the protest in part.