[Protest of Army Acceptance of Bid Corrections]

B-248007.2: Sep 3, 1992

Additional Materials:

Contact:

Office of Public Affairs
(202) 512-4800
youngc1@gao.gov

A firm protested the Army's decision to permit the awardee to correct mistakes in its bid on a contract for the construction of a water channel, contending that the awardee and its subcontractor did not provide clear and convincing evidence of its intended bid. GAO held that the Army: (1) could not reasonably find clear and convincing evidence to support the amounts assigned to particular items; and (2) incorrectly permitted the awardee to correct its bid. Accordingly, the protest was sustained, and GAO recommended that the Army: (1) modify the awarded contract to reflect the original bid; and (2) reimburse the protester for its protest costs.